Vietnam Data Center Market 2027-2032: Foreign Ownership Rules, Capacity Pipeline and Power Constraints

JakartaMarketLab | Research Division

Vietnam Data Center Market 2027-2032: Foreign Ownership Rules, Capacity Pipeline and Power Constraints

Vietnam is the most underserved data centre market in Asia-Pacific, with roughly 1.4 million people for every megawatt of live capacity. A 2023 telecom law opened the sector to full foreign ownership, billions of dollars of projects followed, and the binding question is now whether the power grid can keep up. This review covers capacity, the project pipeline, regulation, power, costs and the operators building the market.
Date: November 2026
Base Year: 2025
Forecast Period: 2027-2032
Geography: Vietnam
Pages: 42 slides
Illustration of server racks, a transmission tower and power lines representing Vietnam's data centre market
~372.75 MW
Designed capacity of 42 data centres, May 2026 (MOST)
~148 MW
Operational capacity (BMI estimate)
100%
Foreign ownership allowed for onshore data centre services
~US$7.2M
Average build cost per MW (Cushman & Wakefield)
XX.X%
2027-2032 forecast CAGR, colocation revenue

Market Overview

Vietnam's data centre market is small for a country of more than 100 million people, but it is growing quickly from a low base. The Ministry of Science and Technology (MOST) counted 42 data centres with a total designed capacity of about 372.75 MW in May 2026, more than four times the 2021 level. Designed capacity, however, overstates what is actually running. Estimates of live IT capacity range from about 100 MW (Viet Nam News, late 2025) to about 148 MW (BMI, mid-2026), concentrated almost entirely in Hanoi and Ho Chi Minh City.

The gap between figures is a definitional issue that buyers and investors should keep in mind. Some sources quote total electrical power, some quote designed capacity including phases not yet built, and others quote IT load, the power available to servers. In this review we use IT load wherever possible, because it is the figure that drives revenue and customer capacity.

Vietnam data centre capacity, MW (different definitions)
Mar 2025 total
182.0
Jul 2025 active power
221.0
Late 2025 IT live
100.0
Mid-2026 IT live (BMI)
148.0
May 2026 designed
372.75
Source: Ministry of Science and Technology via VnExpress (Mar 2025) and Viet Nam News (May 2026); US ITA citing MOST (Jul 2025); Viet Nam News (late 2025); BMI via TechNode Global (Jul 2026). Figures use different definitions and are not directly comparable.

Compared with regional hubs, Vietnam is far behind. Viet Nam News puts Shanghai at about 1,070 MW of operational capacity and Singapore at about 740 MW. Cushman & Wakefield's 2026 Asia-Pacific Data Centre Investment Landscape calls Vietnam the region's most underserved market, with about 1.4 million people per MW of operational capacity. That gap is the core investment case: demand from cloud, e-commerce, banking, gaming and government digitalisation is rising faster than supply.

IndicatorValueSource
Data centres (MOST count)42MOST, May 2026
Designed capacity~372.75 MWMOST, May 2026
Operational IT capacity~148 MWBMI, Jul 2026
Under construction~79 MWBMI, Jul 2026
Announced or planned>870 MWBMI, Jul 2026
2030 national target~870 MWMOST
Colocation revenue, 2026E (JML)US$ XXX M████
Average wholesale rate per kW/month, 2026EUS$ XXX████
Operational IT capacity, 2032 base caseXXX MW████
Source: as listed. Locked figures: JakartaMarketLab estimates, results of extrapolation/triangulation using MOST, BMI, Cushman & Wakefield, JLL and company data.
How large will Vietnam's live data centre capacity and colocation revenue be by 2032?
The full report answers this with complete tables, year-by-year data, charts and analyst commentary, plus outlook scenarios to 2032.
Request the full report

Foreign Ownership Rules and Regulation

The most important regulatory change of the past few years is the Law on Telecommunications No. 24/2023/QH15, passed in November 2023. It took effect on 1 July 2024, with its provisions on data centre, cloud and over-the-top (OTT) services taking effect on 1 January 2025. For the first time, data centre services were defined in law as value-added telecom services, and, following what Baker McKenzie describes as a light-touch approach, the law imposed no foreign ownership cap on them. A foreign investor can now set up a wholly owned subsidiary to provide data centre services in Vietnam.

Decree 163/2024/ND-CP, issued on 24 December 2024, filled in the details. Data centre operators must register or notify the telecom authority of the services they provide, and must meet technical, security and data protection rules. Separately, the Data Law (effective 1 July 2025) and the Personal Data Protection Law (effective 1 January 2026) set rules on data classification, local storage and cross-border transfer, which the US International Trade Administration expects to increase demand for local data storage.

InstrumentEffectiveWhat it means for data centres
Telecommunications Law 2023 (24/2023/QH15)1 Jul 2024; DC provisions 1 Jan 2025DC services defined as value-added telecom; no foreign ownership cap
Decree 163/2024/ND-CPDec 2024Registration/notification with telecom authority; light-touch licensing
Data Law1 Jul 2025Data classification; rules on important and core data
Personal Data Protection Law1 Jan 2026Supports local storage demand; cross-border transfer rules
Resolution 57 (Dec 2024)2024-2030Science, technology and digital transformation push; digital economy target of 30% of GDP
Circular 60/2025/TT-BCT and MOIT guidance (Apr 2026)Dec 2025 / Apr 2026Electricity tariff classification for data centres
Source: Baker McKenzie (Feb 2024); KPMG Vietnam (Dec 2024); Tilleke & Gibbins; US ITA; Viet Nam News; VietnamNet.

In practice, the opening has already changed the investor mix. Before 2024, foreign players mostly entered through partnerships with Vietnamese telecom groups, such as ST Telemedia's 60 MW joint project with VNG. Since 2025, foreign developers and capital have announced their own projects, including Singapore-based developers and AI infrastructure funds. Some uncertainty remains around data sovereignty rules for state and financial data, which in practice favour domestic, state-linked operators for government workloads.

Which workloads can foreign operators serve, and how will data rules shape demand to 2032?
The full report answers this with complete tables, year-by-year data, charts and analyst commentary, plus outlook scenarios to 2032.
Request the full report

Capacity Pipeline: From 30 MW Halls to Hyperscale Campuses

Until recently, almost every Vietnamese data centre was a small enterprise or colocation facility of a few megawatts. VnExpress reported in mid-2025 that the country had only one operational hyperscale data centre, of about 30 MW. The pipeline now looks very different. BMI counts about 79 MW under construction and more than 870 MW announced or planned, and estimates that Vietnam has attracted more than US$7 billion of announced and proposed AI and data centre investment.

ProjectSponsorLocationCapacityStatus / timing
Tan Phu Trung hyperscaleViettel IDCHCMC (Cu Chi)140 MW, ~10,000 racksUnder construction since Apr 2025; phased to 2030
An Khanh data centreViettelHanoiVND 17.5 trillion (~US$665M)Phase 1 targeted Q2 2026
CMC Hyperscale DCCMC CorporationSaigon Hi-Tech Park30 MW initial, up to 120 MWUS$250M+; construction from 2026
VNG-STT data centreVNG, ST TelemediaHCMC60 MWExpected 2026
G42-led consortiumG42, FPT, VinaCapital, Viet ThaiHCMCUp to US$2BAnnounced Feb 2026
Kinh Bac AI data centreKBC, Accelerated Infrastructure CapitalNorth Vietnam~200 MW, ~US$2.1BAnnounced Mar 2026
Starmason hyperscaleStarmason-Up to 60 MW IT, US$480MAnnounced Apr 2026
Evolution, Hathor, FrontierSingapore developersHCMC52 MW IT, US$509MAnnounced Apr 2026
SDP hyperscale campusDeveloper advised by Cushman & Wakefield-300 MW by 2030 (initial)Planning
Probability-weighted pipeline delivered by 2030XXX MW████████████
Source: Hanoi Times; VnExpress; The Investor; US ITA; Viet Nam News; Tuoi Tre (JLL); Cushman & Wakefield. Capacities are as announced and may refer to total power or IT load.

Ho Chi Minh City is where most of the new supply is heading. Cushman & Wakefield counted 33 MW of operational IT capacity across 14 facilities and nine providers in the city in the first half of 2026, with a pipeline of 68 MW (14 MW under construction and 54 MW planned), more than double existing capacity. BMI has raised its estimate of planned capacity in the city to nearly 375 MW. Hanoi remains the centre of government and state-owned enterprise demand, with Hoa Lac Hi-Tech Park hosting several new facilities.

Viettel IDC's own projection is that Vietnam's capacity will grow five to six times from current levels to nearly 600 MW by 2030. Not all announced projects will be built on schedule; the history of the region suggests that a large share of announcements slips, shrinks or is cancelled, especially when power is not secured early.

Vietnam operational IT capacity by city (Hanoi, HCMC, other) and by operator type, 2025-2032, base case
πŸ”’ In the full report

Power: The Binding Constraint

Every serious analysis of the Vietnamese market now comes back to electricity. Data centres currently use only about 0.5% of Vietnam's electricity, against an estimated 2-6% in the US, according to the Institute of Energy under the Ministry of Industry and Trade. But the national system is already tight. In September 2026 the Ministry of Industry and Trade warned that Vietnam could face a shortfall of about 61 billion kWh in 2030, with the gap widening after 2027, as demand from data centres, AI, semiconductor plants and electrified transport outpaces delayed generation and grid projects.

For individual projects, the issue is connection time. A 100 MW project in a major cluster faces a wait of about two to three years for new supply, according to a report cited by VnExpress, and land suitable for data centres typically costs 30-50% more than ordinary industrial land because of power, fibre and substation requirements. Developers are responding by moving to sites that can be supplied with large blocks of power, by planning on-site substations, and by exploring direct power purchase agreements (DPPAs) for renewable energy.

Power issueCurrent situationImplication
National supply gap~61 billion kWh shortfall risk in 2030 (MOIT)Large projects need early grid commitments
Grid connection for 100 MW~2-3 years wait in main clustersPhasing and site choice are critical
Electricity tariffsDispute over commercial vs industrial tariff (Circular 60, 2025)Opex risk until rules settle
Renewable sourcingDPPA framework improving; first virtual DPPA dealsSupports hyperscaler sustainability goals
Data centre share of national demand~0.5% todayWill rise sharply with hyperscale campuses
Data centre share of national demand, 2032EX.X%████
Source: Ministry of Industry and Trade via The Nation and Viet Nam News (Sep 2026); VnExpress; VietnamNet; Chambers Global Practice Guide (2026); Institute of Energy.

Tariffs have become a live dispute. After Circular 60/2025/TT-BCT, some power companies classified data centres as centralised data processing services and applied commercial electricity tariffs, which are higher than industrial ones. Viettel, VNPT, FPT Telecom, CMC and VNG Data Center jointly asked the Ministry of Industry and Trade to revise this, and the ministry issued guidance to EVN in April 2026. The Ministry of Science and Technology has since pressed several times for uniform industrial rates, and EVNHCMC has reported payment disputes with two operators. Because electricity is the largest operating cost of a data centre, the outcome matters directly for pricing and margins.

How much power will Vietnam's data centres need by 2032, and where can it be supplied?
The full report answers this with complete tables, year-by-year data, charts and analyst commentary, plus outlook scenarios to 2032.
Request the full report

Costs and Competitive Landscape

Vietnam's strongest selling point after demand is cost. Cushman & Wakefield estimates construction costs of US$5.7-8.7 million per MW in Vietnam, averaging about US$7.2 million, against a regional range of US$7.9-19.2 million and about US$17.9 million in Singapore, with annual construction cost inflation of about 3.8%. Labour, land outside prime clusters and engineering services are all cheaper than in Singapore, Japan or Australia.

Data centre construction cost, US$ million per MW
Vietnam (avg)
7.2
APAC low end
7.9
Singapore
17.9
Japan
19.2
Source: Cushman & Wakefield Asia Pacific Data Centre Construction Cost Guide, via Viet Nam News and VietnamNet (2026).

The market is highly concentrated. Five players, mostly telecom operators and state-owned enterprises, control about 97% of capacity, according to a late-2025 analysis cited by DTiNews: Viettel IDC leads with about 41% (around 42 MW), followed by VNPT with about 25 MW, then FPT Telecom, CMC Telecom and a smaller group that includes VNG, NTT DATA, Hanoi Telecom, VNTT and others. Foreign operators such as ST Telemedia, NTT DATA and new Singapore-based developers are expanding, but domestic groups still own most live capacity.

OperatorTypeFootprintNotes
Viettel IDCState-owned (military) telecom15+ data centres; 140 MW Tan Phu TrungMarket leader (~41% share)
VNPTState-owned telecom8th DC opened at Hoa Lac (2,000 racks)No. 2 (~25 MW)
FPT Telecom (FPT Fornix)Private4 large DCs (HN01, HN02, HCM01, HCM02)HCM02 has the most racks in Vietnam
CMC TelecomPrivateHanoi and HCMC; hyperscale projectUp to 120 MW planned
VNG / STTPrivate + foreign JV60 MW HCMC projectGaming and cloud demand
Foreign developers (G42, STT, NTT DATA, others)ForeignMultiple announcementsEnabled by ownership opening
Market share in 2030 (JML)XX%████████
Source: DTiNews; Hanoi Times; VnExpress; The Investor; US ITA; company information.

What This Means for Operators, Suppliers and Investors

  • Foreign operators and developers: full foreign ownership is now possible, but power and land are the real gates. Secure grid commitments and phased capacity before announcing large campuses.
  • Hyperscalers and cloud providers: Vietnam offers low build costs and an underserved market; domestic partners still matter for government and regulated workloads.
  • Equipment suppliers: cooling suited to a tropical climate, power distribution, substations, UPS and on-site generation will be in high demand as hyperscale projects start.
  • Investors: watch the tariff decision for data centres, DPPA progress and the delivery rate of announced projects; these decide returns more than headline demand.
  • Asian partners: Japanese, Korean, Singaporean and Thai firms can supply capital, engineering and operations expertise, or bring anchor tenants.

For related coverage, see our Data Centers & Digital Infrastructure reports and other Vietnam market research on JakartaMarketLab.

Key Questions Answered in the Full Report

  1. How much live data centre capacity does Vietnam have, and how fast will it grow?
  2. Can foreign companies own and operate data centres in Vietnam?
  3. Which projects in the pipeline are likely to be delivered by 2030?
  4. How will power supply and electricity tariffs affect projects?
  5. Who are the leading operators and what are their shares?
  6. What are the bear, base and bull forecasts for 2027-2032?
See the answers in the full report

Vietnam Data Center Market 2027-2032: Foreign Ownership Rules, Capacity Pipeline and Power Constraints Executive Summary

The three slides below summarise the full report. The complete 42-slide version, with the outlook to 2032, regulation, value chain and company profiles, is available as a PDF.

Executive Summary · 1 / 3 · Headline numbers
Vietnam Data Center Market Executive Summary
~148 MW
Live IT capacity (BMI)
████
Colocation revenue 2026E
████
IT capacity 2032
████
2027-2032 CAGR
  • Most underserved market in APAC.
  • 100% foreign ownership allowed.
  • Pipeline above 870 MW.
JakartaMarketLab · www.jakartamarketlab.comSource: JML estimates (triangulated from ministry, consultancy and company data)
Executive Summary · 2 / 3 · Power
The binding constraint
2-3 yrs
Wait for 100 MW connection
~0.5%
DC share of power use
████
DC power demand 2032
████
Tariff scenario impact
  • National supply gap after 2027.
  • Tariff dispute ongoing.
  • DPPA improving.
JakartaMarketLab · www.jakartamarketlab.comSource: JML estimates (triangulated from ministry, consultancy and company data)
Executive Summary · 3 / 3 · Players
A concentrated market
~41%
Viettel IDC share
~97%
Top-five share
████
Foreign share 2032
████
Hyperscale share 2032
  • Domestic telcos lead.
  • Foreign developers arriving.
  • HCMC pipeline doubles capacity.
JakartaMarketLab · www.jakartamarketlab.comSource: JML estimates (triangulated from ministry, consultancy and company data)

Report Preview

Capacity by city and operator
πŸ”’ In the full report
Colocation pricing and revenue
πŸ”’ In the full report
Porter's Five Forces
πŸ”’ In the full report
Company profiles (top 5)
πŸ”’ In the full report
Who this report is for
Data centre operators, hyperscalers, equipment suppliers, utilities, investors, real estate developers and policy advisers.
Method: secondary research and data triangulation across Ministry of Science and Technology statistics, real estate consultancy reports, company announcements, power sector data and third-party estimates. Base year 2025, estimate 2026, forecasts 2027-2032. Published November 2026.
Request the full report

What the Full Report Includes

This 42-slide report is written for data centre operators, hyperscalers and cloud providers, equipment suppliers, utilities and energy developers, investors and policy advisers following Vietnam's data centre market.
  • Operational, under-construction and planned capacity, 2021-2025 and 2026 estimate
  • Colocation revenue and pricing
  • Regulation: Telecom Law 2023, Decree 163, Data Law, PDPL
  • Project pipeline and delivery probability
  • Power supply, tariffs and DPPA
  • Build costs and economics
  • Value chain, Porter's Five Forces and key mega trends
  • Drivers, restraints and impact assessment
  • Market landscape and shares
  • Profiles of Viettel IDC, VNPT, FPT Telecom, CMC Telecom and VNG/ST Telemedia
  • Bear, base and bull forecasts to 2032
Get the Full Report
Vietnam Data Center Market 2027-2032: Foreign Ownership Rules, Capacity Pipeline and Power Constraints. 42 slides, PDF.
Request the Full Report
Sources
Ministry of Science and Technology data via VnExpress and Viet Nam News; US International Trade Administration Vietnam data centre market intelligence; BMI via TechNode Global (Jul 2026); Cushman & Wakefield APAC Data Centre Update H1 2026 and Investment Landscape 2026; JLL via Tuoi Tre and Viet Nam News; Baker McKenzie, KPMG Vietnam and Tilleke & Gibbins legal updates; Ministry of Industry and Trade via The Nation and Viet Nam News; VietnamNet; Hanoi Times; The Investor; DTiNews; Chambers Global Practice Guide Power 2026.
This article is a promotional summary of a market research report published by JakartaMarketLab. Selected statistics are shown for indicative purposes only. Figures marked as triangulated are JakartaMarketLab estimates and may differ from other published sources. This article is not investment advice.
© 2026 JakartaMarketLab Market Intelligence | www.jakartamarketlab.com | risetlokal@gmail.com