Vietnam Data Center Market 2027-2032: Foreign Ownership Rules, Capacity Pipeline and Power Constraints
Market Overview
Vietnam's data centre market is small for a country of more than 100 million people, but it is growing quickly from a low base. The Ministry of Science and Technology (MOST) counted 42 data centres with a total designed capacity of about 372.75 MW in May 2026, more than four times the 2021 level. Designed capacity, however, overstates what is actually running. Estimates of live IT capacity range from about 100 MW (Viet Nam News, late 2025) to about 148 MW (BMI, mid-2026), concentrated almost entirely in Hanoi and Ho Chi Minh City.
The gap between figures is a definitional issue that buyers and investors should keep in mind. Some sources quote total electrical power, some quote designed capacity including phases not yet built, and others quote IT load, the power available to servers. In this review we use IT load wherever possible, because it is the figure that drives revenue and customer capacity.
Compared with regional hubs, Vietnam is far behind. Viet Nam News puts Shanghai at about 1,070 MW of operational capacity and Singapore at about 740 MW. Cushman & Wakefield's 2026 Asia-Pacific Data Centre Investment Landscape calls Vietnam the region's most underserved market, with about 1.4 million people per MW of operational capacity. That gap is the core investment case: demand from cloud, e-commerce, banking, gaming and government digitalisation is rising faster than supply.
| Indicator | Value | Source |
|---|---|---|
| Data centres (MOST count) | 42 | MOST, May 2026 |
| Designed capacity | ~372.75 MW | MOST, May 2026 |
| Operational IT capacity | ~148 MW | BMI, Jul 2026 |
| Under construction | ~79 MW | BMI, Jul 2026 |
| Announced or planned | >870 MW | BMI, Jul 2026 |
| 2030 national target | ~870 MW | MOST |
| Colocation revenue, 2026E (JML) | US$ XXX M | ████ |
| Average wholesale rate per kW/month, 2026E | US$ XXX | ████ |
| Operational IT capacity, 2032 base case | XXX MW | ████ |
Foreign Ownership Rules and Regulation
The most important regulatory change of the past few years is the Law on Telecommunications No. 24/2023/QH15, passed in November 2023. It took effect on 1 July 2024, with its provisions on data centre, cloud and over-the-top (OTT) services taking effect on 1 January 2025. For the first time, data centre services were defined in law as value-added telecom services, and, following what Baker McKenzie describes as a light-touch approach, the law imposed no foreign ownership cap on them. A foreign investor can now set up a wholly owned subsidiary to provide data centre services in Vietnam.
Decree 163/2024/ND-CP, issued on 24 December 2024, filled in the details. Data centre operators must register or notify the telecom authority of the services they provide, and must meet technical, security and data protection rules. Separately, the Data Law (effective 1 July 2025) and the Personal Data Protection Law (effective 1 January 2026) set rules on data classification, local storage and cross-border transfer, which the US International Trade Administration expects to increase demand for local data storage.
| Instrument | Effective | What it means for data centres |
|---|---|---|
| Telecommunications Law 2023 (24/2023/QH15) | 1 Jul 2024; DC provisions 1 Jan 2025 | DC services defined as value-added telecom; no foreign ownership cap |
| Decree 163/2024/ND-CP | Dec 2024 | Registration/notification with telecom authority; light-touch licensing |
| Data Law | 1 Jul 2025 | Data classification; rules on important and core data |
| Personal Data Protection Law | 1 Jan 2026 | Supports local storage demand; cross-border transfer rules |
| Resolution 57 (Dec 2024) | 2024-2030 | Science, technology and digital transformation push; digital economy target of 30% of GDP |
| Circular 60/2025/TT-BCT and MOIT guidance (Apr 2026) | Dec 2025 / Apr 2026 | Electricity tariff classification for data centres |
In practice, the opening has already changed the investor mix. Before 2024, foreign players mostly entered through partnerships with Vietnamese telecom groups, such as ST Telemedia's 60 MW joint project with VNG. Since 2025, foreign developers and capital have announced their own projects, including Singapore-based developers and AI infrastructure funds. Some uncertainty remains around data sovereignty rules for state and financial data, which in practice favour domestic, state-linked operators for government workloads.
Capacity Pipeline: From 30 MW Halls to Hyperscale Campuses
Until recently, almost every Vietnamese data centre was a small enterprise or colocation facility of a few megawatts. VnExpress reported in mid-2025 that the country had only one operational hyperscale data centre, of about 30 MW. The pipeline now looks very different. BMI counts about 79 MW under construction and more than 870 MW announced or planned, and estimates that Vietnam has attracted more than US$7 billion of announced and proposed AI and data centre investment.
| Project | Sponsor | Location | Capacity | Status / timing |
|---|---|---|---|---|
| Tan Phu Trung hyperscale | Viettel IDC | HCMC (Cu Chi) | 140 MW, ~10,000 racks | Under construction since Apr 2025; phased to 2030 |
| An Khanh data centre | Viettel | Hanoi | VND 17.5 trillion (~US$665M) | Phase 1 targeted Q2 2026 |
| CMC Hyperscale DC | CMC Corporation | Saigon Hi-Tech Park | 30 MW initial, up to 120 MW | US$250M+; construction from 2026 |
| VNG-STT data centre | VNG, ST Telemedia | HCMC | 60 MW | Expected 2026 |
| G42-led consortium | G42, FPT, VinaCapital, Viet Thai | HCMC | Up to US$2B | Announced Feb 2026 |
| Kinh Bac AI data centre | KBC, Accelerated Infrastructure Capital | North Vietnam | ~200 MW, ~US$2.1B | Announced Mar 2026 |
| Starmason hyperscale | Starmason | - | Up to 60 MW IT, US$480M | Announced Apr 2026 |
| Evolution, Hathor, Frontier | Singapore developers | HCMC | 52 MW IT, US$509M | Announced Apr 2026 |
| SDP hyperscale campus | Developer advised by Cushman & Wakefield | - | 300 MW by 2030 (initial) | Planning |
| Probability-weighted pipeline delivered by 2030 | XXX MW | ████ | ████ | ████ |
Ho Chi Minh City is where most of the new supply is heading. Cushman & Wakefield counted 33 MW of operational IT capacity across 14 facilities and nine providers in the city in the first half of 2026, with a pipeline of 68 MW (14 MW under construction and 54 MW planned), more than double existing capacity. BMI has raised its estimate of planned capacity in the city to nearly 375 MW. Hanoi remains the centre of government and state-owned enterprise demand, with Hoa Lac Hi-Tech Park hosting several new facilities.
Viettel IDC's own projection is that Vietnam's capacity will grow five to six times from current levels to nearly 600 MW by 2030. Not all announced projects will be built on schedule; the history of the region suggests that a large share of announcements slips, shrinks or is cancelled, especially when power is not secured early.
Power: The Binding Constraint
Every serious analysis of the Vietnamese market now comes back to electricity. Data centres currently use only about 0.5% of Vietnam's electricity, against an estimated 2-6% in the US, according to the Institute of Energy under the Ministry of Industry and Trade. But the national system is already tight. In September 2026 the Ministry of Industry and Trade warned that Vietnam could face a shortfall of about 61 billion kWh in 2030, with the gap widening after 2027, as demand from data centres, AI, semiconductor plants and electrified transport outpaces delayed generation and grid projects.
For individual projects, the issue is connection time. A 100 MW project in a major cluster faces a wait of about two to three years for new supply, according to a report cited by VnExpress, and land suitable for data centres typically costs 30-50% more than ordinary industrial land because of power, fibre and substation requirements. Developers are responding by moving to sites that can be supplied with large blocks of power, by planning on-site substations, and by exploring direct power purchase agreements (DPPAs) for renewable energy.
| Power issue | Current situation | Implication |
|---|---|---|
| National supply gap | ~61 billion kWh shortfall risk in 2030 (MOIT) | Large projects need early grid commitments |
| Grid connection for 100 MW | ~2-3 years wait in main clusters | Phasing and site choice are critical |
| Electricity tariffs | Dispute over commercial vs industrial tariff (Circular 60, 2025) | Opex risk until rules settle |
| Renewable sourcing | DPPA framework improving; first virtual DPPA deals | Supports hyperscaler sustainability goals |
| Data centre share of national demand | ~0.5% today | Will rise sharply with hyperscale campuses |
| Data centre share of national demand, 2032E | X.X% | ████ |
Tariffs have become a live dispute. After Circular 60/2025/TT-BCT, some power companies classified data centres as centralised data processing services and applied commercial electricity tariffs, which are higher than industrial ones. Viettel, VNPT, FPT Telecom, CMC and VNG Data Center jointly asked the Ministry of Industry and Trade to revise this, and the ministry issued guidance to EVN in April 2026. The Ministry of Science and Technology has since pressed several times for uniform industrial rates, and EVNHCMC has reported payment disputes with two operators. Because electricity is the largest operating cost of a data centre, the outcome matters directly for pricing and margins.
Costs and Competitive Landscape
Vietnam's strongest selling point after demand is cost. Cushman & Wakefield estimates construction costs of US$5.7-8.7 million per MW in Vietnam, averaging about US$7.2 million, against a regional range of US$7.9-19.2 million and about US$17.9 million in Singapore, with annual construction cost inflation of about 3.8%. Labour, land outside prime clusters and engineering services are all cheaper than in Singapore, Japan or Australia.
The market is highly concentrated. Five players, mostly telecom operators and state-owned enterprises, control about 97% of capacity, according to a late-2025 analysis cited by DTiNews: Viettel IDC leads with about 41% (around 42 MW), followed by VNPT with about 25 MW, then FPT Telecom, CMC Telecom and a smaller group that includes VNG, NTT DATA, Hanoi Telecom, VNTT and others. Foreign operators such as ST Telemedia, NTT DATA and new Singapore-based developers are expanding, but domestic groups still own most live capacity.
| Operator | Type | Footprint | Notes |
|---|---|---|---|
| Viettel IDC | State-owned (military) telecom | 15+ data centres; 140 MW Tan Phu Trung | Market leader (~41% share) |
| VNPT | State-owned telecom | 8th DC opened at Hoa Lac (2,000 racks) | No. 2 (~25 MW) |
| FPT Telecom (FPT Fornix) | Private | 4 large DCs (HN01, HN02, HCM01, HCM02) | HCM02 has the most racks in Vietnam |
| CMC Telecom | Private | Hanoi and HCMC; hyperscale project | Up to 120 MW planned |
| VNG / STT | Private + foreign JV | 60 MW HCMC project | Gaming and cloud demand |
| Foreign developers (G42, STT, NTT DATA, others) | Foreign | Multiple announcements | Enabled by ownership opening |
| Market share in 2030 (JML) | XX% | ████ | ████ |
What This Means for Operators, Suppliers and Investors
- Foreign operators and developers: full foreign ownership is now possible, but power and land are the real gates. Secure grid commitments and phased capacity before announcing large campuses.
- Hyperscalers and cloud providers: Vietnam offers low build costs and an underserved market; domestic partners still matter for government and regulated workloads.
- Equipment suppliers: cooling suited to a tropical climate, power distribution, substations, UPS and on-site generation will be in high demand as hyperscale projects start.
- Investors: watch the tariff decision for data centres, DPPA progress and the delivery rate of announced projects; these decide returns more than headline demand.
- Asian partners: Japanese, Korean, Singaporean and Thai firms can supply capital, engineering and operations expertise, or bring anchor tenants.
For related coverage, see our Data Centers & Digital Infrastructure reports and other Vietnam market research on JakartaMarketLab.
Key Questions Answered in the Full Report
- How much live data centre capacity does Vietnam have, and how fast will it grow?
- Can foreign companies own and operate data centres in Vietnam?
- Which projects in the pipeline are likely to be delivered by 2030?
- How will power supply and electricity tariffs affect projects?
- Who are the leading operators and what are their shares?
- What are the bear, base and bull forecasts for 2027-2032?
Vietnam Data Center Market 2027-2032: Foreign Ownership Rules, Capacity Pipeline and Power Constraints Executive Summary
The three slides below summarise the full report. The complete 42-slide version, with the outlook to 2032, regulation, value chain and company profiles, is available as a PDF.
- Most underserved market in APAC.
- 100% foreign ownership allowed.
- Pipeline above 870 MW.
- National supply gap after 2027.
- Tariff dispute ongoing.
- DPPA improving.
- Domestic telcos lead.
- Foreign developers arriving.
- HCMC pipeline doubles capacity.
Report Preview
What the Full Report Includes
- Operational, under-construction and planned capacity, 2021-2025 and 2026 estimate
- Colocation revenue and pricing
- Regulation: Telecom Law 2023, Decree 163, Data Law, PDPL
- Project pipeline and delivery probability
- Power supply, tariffs and DPPA
- Build costs and economics
- Value chain, Porter's Five Forces and key mega trends
- Drivers, restraints and impact assessment
- Market landscape and shares
- Profiles of Viettel IDC, VNPT, FPT Telecom, CMC Telecom and VNG/ST Telemedia
- Bear, base and bull forecasts to 2032